ANTSPACE HK3 V7 Dry tower example with broader HK3 platform references

Bitmain ANTSPACE HK3 V7 Dry Tower Guide

Download the Bitmain ANTSPACE HK3 V7 dry tower manual for the current HK3 branch. It covers the higher power envelope, 650 kW dry tower specification, and the added exhaust air-conditioning kit section.

Manual revision V7
Server class 210 S21/S19 Hydro units
Container power 1200 kW operating / 1300 kW max
Dry tower capacity 650 kW
HK3 V7 hydro infrastructure guide

The HK3 V7 manual is the current Bitmain guide for the HK3 dry tower branch.

V7 raises the container-side power envelope, keeps 210 S21/S19 Hydro servers in the chassis, and adds an exhaust air-conditioning kit installation section missing from the V6 dry tower manual.

PDF Download

Download the Bitmain ANTSPACE HK3 V7 Dry Tower Guide PDF

Download the PDF, then use the sections below to review specs, setup steps, power and cooling requirements, maintenance notes, troubleshooting details, and revision history for Bitmain ANTSPACE HK3 V7 Dry Tower Guide.

V7 October 2024 91 pages

Comparison

Bitmain ANTSPACE HK3 V7 Dry Tower Guide: Version Differences

  • HK3 V7 raises the container-side operating and maximum power versus HK3 V6 dry tower while keeping the same 6058 x 2438 x 2896 mm chassis footprint.
  • The dry tower branch is rated at 650 kW here, which is higher than the 500 kW dry tower rating documented in the V6 dry tower manual.
  • The V7 manual includes a dedicated 'Installing Exhaust Air-conditioning Kit for Container' section that does not appear in the V6 dry tower manual.
  • V7 treats HK3 as a current platform with dry-wet, dry tower, and PHE options called out in the system overview.

Quick Specs

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Specs and Requirements

Container dimensions 6058 x 2438 x 2896 mm
High-computing server capacity 210 S21 Hyd. and S19 Hyd. series servers
Operating / max power 1200 kW / 1300 kW
Dry tower heat dissipation 650 kW
Dry tower power / noise 20-32 kW, 70 dBA @ 25C and 15 m
Interfaces / flow DN125 tower interface, DN100 heating/PHE interface, >=85 m3/h flow

Installation

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Setup Highlights

  • Level the container, install the dry tower, and route the connecting pipes using the V7 placement and installation drawings.
  • Install the exhaust fans and the exhaust air-conditioning kit for the container if the field build includes that package.
  • Use the V7 power distribution section rather than back-porting earlier assumptions from V6 or the grouped HK3 manuals.
  • Close out startup with the onsite installation summary before moving into power-on sequencing.

Utilities

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Power and Cooling Requirements

  • The V7 manual explicitly states that the HK3 platform can work with dry-wet tower, PHE, or dry tower heat-rejection options, even though this document uses the dry tower variant as the example.
  • Container-side power rises to 1200 kW operating and 1300 kW maximum in the V7 performance table.
  • The dry tower branch is rated for 650 kW of heat dissipation with 20-32 kW operating power.
  • Flow remains at >=85 m3/h and the interface strategy still separates DN125 tower piping from the DN100 heating/PHE interface.

Operations

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Operation Notes

  • The V7 manual includes system pressurization, liquid replenishment, electrical wiring, system power-on/power-off, and touch-screen operation sections in one product manual.
  • Field teams can use the broader V7 overview to understand how the HK3 platform relates to other heat-rejection options, even when the actual build is dry tower.
  • The onsite installation summary is included in the operations part of the document so commissioning and operation stay connected.
  • Because V7 is newer, it is the best dry tower reference for current HK3 procurement and launch planning.

Maintenance

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Maintenance Notes

  • V7 retains dedicated dry tower troubleshooting and dry tower maintenance chapters.
  • Sites running newer HK3 dry tower equipment should stay on this manual when the V6 split manuals no longer match the field labels or options.
  • The maintenance structure is cleaner than the older grouped HK3 manuals and more current than the V6 dry tower branch.
  • The air-conditioning kit section is another indicator that V7 is meant for a slightly more feature-complete current generation of HK3 deployments.

Troubleshooting

Bitmain ANTSPACE HK3 V7 Dry Tower Guide Troubleshooting Notes

  • Container faults and dry tower faults are separated into dedicated troubleshooting sections.
  • The safest way to distinguish V7 from V6 in the field is usually the combination of the higher power table and the added exhaust air-conditioning kit section.
  • Use the V7 manual before assuming a current HK3 container behaves exactly like the earlier split-manual V6 branch.

Files

Bitmain ANTSPACE HK3 V7 Dry Tower Guide PDF Download and Revision History

Product Manual

HK3 V7 Dry Tower Product Manual

Current HK3 V7 dry tower manual covering the higher power profile and exhaust air-conditioning kit section.

Version
V7
Date
October 2024
Pages
91

Revision Archive

  • HK3 V7 dry tower manual V7 · October 2024

    Current-generation HK3 dry tower guide with the updated power envelope and exhaust air-conditioning kit install section.

Next Steps

Keep Exploring ANTSPACE and Hydro Content

Need Help Planning a Bitmain Hydro Container Deployment?

We can help you compare HK3, HW5, and HD5 platforms, sort out utilities and heat rejection, and align the right manual with the hardware you have in the field.