ANTSPACE HK3 V6 Dry tower

Bitmain ANTSPACE HK3 V6 Dry Tower Guide

Download the Bitmain ANTSPACE HK3 V6 dry tower manual for the first cooling-method-specific HK3 branch. It covers dry tower installation, interfaces, commissioning, and maintenance for the split V6 platform.

Manual revision V2.0.5
Server class 210 S21/S19 Hydro units
Tower capacity 500 kW
Container power 1047-1050 kW
Hydro mining container

The HK3 V6 dry tower manual marks the point where Bitmain stopped using one grouped HK3 document and started publishing cooling-method manuals.

Use this guide when you need dry tower placement rules, interface details, and dry-tower-specific troubleshooting. HK3 V7 adds a higher power envelope and an exhaust air-conditioning kit section.

PDF Download

Download the Bitmain ANTSPACE HK3 V6 Dry Tower Guide PDF

Download the PDF, then use the sections below to review specs, setup steps, power and cooling requirements, maintenance notes, troubleshooting details, and revision history for Bitmain ANTSPACE HK3 V6 Dry Tower Guide.

V2.0.5 April 2024 105 pages

Comparison

Bitmain ANTSPACE HK3 V6 Dry Tower Guide: Version Differences

  • HK3 V6 dry tower is the first branch in the HK3 line to get its own cooling-method-specific product manual.
  • It keeps the 210-unit HK3 container and roughly 1.05 MW container power profile, but the heat-rejection branch is narrowed to a 500 kW dry tower.
  • The dry tower product manual stands on its own and includes dry-tower-specific maintenance and fault handling.
  • HK3 V7 raises dry tower heat dissipation and adds an exhaust air-conditioning kit section that does not appear here.

Quick Specs

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Specs and Requirements

Container dimensions 6058 x 2438 x 2896 mm
High-computing server capacity 210 S21 Hyd. and S19 Hyd. series servers
Standard / max power 1047 kW / 1050 kW
Dry tower heat dissipation 500 kW
Input power AC 400V±5%, 60Hz/50Hz
Interfaces / flow DN125 dry-tower interface, DN100 heating/PHE interface, >=85 m3/h flow

Installation

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Setup Highlights

  • Level the container before installation, then remove the dry tower panels and hoist the tower into final position.
  • Plan for a 25-ton foundation and at least 2 meters of clearance between the container and the dry tower.
  • Keep the dry tower top unobstructed and align the tower and container pipe-connection surfaces on the same projected line.
  • Install the middle connecting pipes, exhaust fans, and power distribution hardware in the order the manual lays out.

Utilities

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Power and Cooling Requirements

  • The V6 dry tower branch keeps the HK3 container at 1047-1050 kW while giving the dry tower its own dedicated 500 kW dissipation spec.
  • The manual still references DN100 heating/PHE interfaces because the underlying container platform can be adapted, but this product manual is written for the dry tower path.
  • Flow planning remains at >=85 m3/h, matching the container-side pump and manifold expectations.
  • Use the dry tower placement rules and cable/piping alignment diagram rather than reusing the older grouped-HK3 assumptions blindly.

Operations

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Operation Notes

  • The manual includes dedicated sections for system pressurization, liquid replenishment, electrical wiring, power-on/power-off, and touch-screen operation.
  • Dry tower operation is framed around forced-air heat rejection rather than wet spray-water or cold-side water loop management.
  • Commissioning should confirm container and tower behavior together, not as separate subcontractor sign-offs.
  • The tower-side automatic exhaust and drain valve locations are called out during installation and matter again during operations.

Maintenance

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Maintenance Notes

  • The V6 dry tower manual includes dry-tower-specific preventive maintenance and regular inspection sections.
  • Sites with forced-air tower equipment and no wet tower water makeup or PHE cold-side loop should stay on this manual.
  • The troubleshooting and maintenance chapters are narrower than the grouped HK3 manual and more useful for dry-tower-only crews.
  • Technicians should note the split-manual change history because older service habits from the grouped HK3 docs can miss dry-tower-specific checks.

Troubleshooting

Bitmain ANTSPACE HK3 V6 Dry Tower Guide Troubleshooting Notes

  • The manual separates container faults from dry tower faults, which makes it cleaner than the older grouped HK3 O&M document.
  • Use the V6 dry tower guide instead of the dry-wet or PHE manuals when diagnosing forced-air tower faults.
  • The tower fins and exposed valve hardware are called out repeatedly as handling risks during service.

Files

Bitmain ANTSPACE HK3 V6 Dry Tower Guide PDF Download and Revision History

Product Manual

HK3 V6 Dry Tower Product Manual

Change history notes the 2024 split into cooling-method-specific manuals.

Version
V2.0.5
Date
April 2024
Pages
105

Revision Archive

  • Dry tower product manual V2.0.5 · April 2024

    Change history references the move from a shared HK3 manual lineage into cooling-method-specific manuals.

Next Steps

Keep Exploring ANTSPACE and Hydro Content

Need Help Planning a Bitmain Hydro Container Deployment?

We can help you compare HK3, HW5, and HD5 platforms, sort out utilities and heat rejection, and align the right manual with the hardware you have in the field.